Downtown Water Main Replacement Project
Project Update: 
March 8th, 2012

FINAL UPDATE

All of the water mains for the project are now complete and have been activated. All of the sidewalk areas have also been restored. Hand railing at various locations will be installed over the next two weeks. Paving is scheduled for the first week in April whereupon the temporary paving patches will be removed and permanent paving made. On the sidestreets, the streets will have a half-street pavement overlay..

Date

Work Performed

Progress

9/6 - 9/14 Mobilization, locate existing utilities  COMPLETED
9/15 - 10/11 Bore 4 crossings at 220th, 222nd, 225th and 226th   COMPLETED
10/12 - 10/20 MVD water main between 226th and 227th COMPLETED
10/19 - 10/20 226th water main between MVD and 7th COMPLETED
11/2 - 12/2 MVD water main between 225th and 226th COMPLETED
11/9 - 11/11 225th water main between MVD and 7th COMPLETED
11/18 - 12/14 MVD water main between 223rd and 225th COMPLETED
12/7 - 12/15 222nd water main between MVD and 7th COMPLETED
     
12/15 - 12/23 222nd water main between MVD and 7th COMPLETED
12/7 - 2/15 MVD water main between 223rd and 222nd COMPLETED
1/18 - 2/15 MVD water main between 222nd and 220th COMPLETED
2/8 - 2/15 MVD water main between 220th and 219th COMPLETED
2/1 - 2/8 Final testing and connections COMPLETED
4/2 - 4/6 Paving and pavement markings  
4/9 - 4/13 Cleanup and demobilize  
     

Thank you in advance for your patience during this very important project. If you have any questions regarding this project, please feel free to call Loren Reinhold, Project Manager at (206) 870-6524 or Ken Deuman, the District’s project inspector at (425) 985-2302. Dave Maresh, the City’s inspector can also be contacted at (206) 870-6566.

Project Description

The project provides for approximately 4,400 lineal feet of new 12-inch water main, including four 100 foot directional borings below Marine View Drive at 220th Street, 222nd Street, 225th Street and 226th Street.  Approximately 3,000 lineal feet will be under the west sidewalk or outside of the road fog line on Marine View Drive and 1,000 lineal feet will be on the four side streets (220th, 222nd, 225th and 226th) between Marine View Drive and 7th Avenue connecting to the existing water mains on the east side of Marine View Drive. 

  

Project Archives:
Update: January 26, 2012
Update: December 16, 2011
Update: December 2, 2011
Update: November 3, 2011
Update: October 13, 2011

Update: October 6, 2011
Update: September 28, 2011
Update: September 21, 2011


 
 
 
  • Sept 6 Newsletter
  •  
     
     

    Top

    View our Privacy Policy

      
    Flagger Sign
       
    CPF Marketing Communications