City of Des Moines FINAL UPDATE All of the water mains for the project are now complete and have been activated. All of the sidewalk areas have also been restored. Hand railing at various locations will be installed over the next two weeks. Paving is scheduled for the first week in April whereupon the temporary paving patches will be removed and permanent paving made. On the sidestreets, the streets will have a half-street pavement overlay..
Thank you in advance for your patience during this very important project. If you have any questions regarding this project, please feel free to call Loren Reinhold, Project Manager at (206) 870-6524 or Ken Deuman, the District’s project inspector at (425) 985-2302. Dave Maresh, the City’s inspector can also be contacted at (206) 870-6566.
The project provides for approximately 4,400 lineal feet
of new 12-inch water main, including four 100 foot directional
borings below Marine View Drive at 220th
Street, 222nd Street, 225th Street and 226th
Street.
Approximately 3,000 lineal feet will be under the west sidewalk
or outside of the road fog line on Marine View Drive and 1,000
lineal feet will be on the four side streets (220th,
222nd, 225th and 226th) between
Marine View Drive and 7th Avenue connecting to the
existing water mains on the east side of Marine View Drive.